Permit Holders

  1. Submission of quarterly report on studies being undertaken as prescribed in Schedule 2,

 Generation Licensees

  1. Submission of a quarterly report on progress of project by Generation Licensees at Construction Stage as prescribed in Schedule 3,
  2. Submission of quarterly report on key performance indicators as prescribed in Schedule 4,
  3. Submission of quarterly report on power outages as prescribed in Schedule 5,

 Transmission Licensees

  1. Submission of a quarterly report on quality of supply, power system and key performance indicators as prescribed in Schedule 6,
  2. Submission of quarterly report on load shedding and power outage as prescribed in Schedule 11,
  3. Submission of quarterly report on the effect of their operations on the environment as prescribed under Schedule 12,

 Distribution Licensees

  1. Submission of quarterly report on distribution operations as prescribed in Schedule 7,
  2. Submission of quarterly report on network projects undertaken in the quarter as prescribed in Schedule 8,
  3. Submission of quarterly report on compliance with quality of service and system reliability as prescribed in Schedule 9,
  4. Submission of quarterly report on network projects undertaken in the quarter as prescribed in Schedule 8,
  5. Submission of quarterly report on the effect of their operations on the environment as prescribed under Schedule 12,
  6. Submission of an annual report with details of financial performance parameters as prescribed in Schedule 10,
  7. Submission an annual report on consumers who contribute more than five percent of its annual distribution revenue,

 All Licensees

  1. Submission of annual report on the operations and services of the Licensee,
  2. Submission of audited financial statements on an annual basis, and
  3. Submission of Asset Register on an annual basis.